- Client
- Orrery Glass
- Delivery team
- Wren Engineering
Commission
Retuned the cooling cycle on three annealing ovens.
Commissioning notes
Rejects fell from 6.2% to 4.8% in the eight weeks after commissioning.
The target for next spring is 4.0%.
Retuned the cooling cycle on three annealing ovens.
Rejects fell from 6.2% to 4.8% in the eight weeks after commissioning.
The target for next spring is 4.0%.